Project Schedule
The County of Monmouth, with the cooperating agencies of NJTPA and NJDOT, will provide updates in an effort to keep the community and general public informed of current progress on the County Route 537 West Main Street corridor roadway improvements project.
Project Schedule (Phases)
Local Concept Development (LCD) Phase |
2011 – 2014 completed |
Local Preliminary Engineering (LPE) Phase |
2015 – 2019 completed |
Final Design (FD) Phase |
2020 – 2023 |
Construction Phase |
2023 – 2025 |
Final Design Phase – Project Schedule (Major Milestones)
Environmental Permits |
Fall 2021 |
ROW Availability / Easements |
Spring 2023 |
PS&E Plans |
Spring 2023 |
Completion of Final Design Phase |
Summer 2023 |
Final Design Phase – Anticipated Community Involvement Schedule
Local Officials Meetings No. 1 and No. 2 |
February 2021, Winter 2022 |
Community Stakeholders Meetings No. 1 and No. 2 |
September 2021, Spring 2022 |
Public Information Center (PIC) Meeting |
Spring 2023 |
Do you have a comment or suggestion? Are you a new resident or business owner in the area of the project? Feel free to contact us and use the online comment form for questions or comments or to be added to the contact mailing list.